Feasibility study for the Linz natural gas storage station

Expansion of the existing gas storage facility at the Linz DC site to increase storage and supply capacities by integrating a natural gas compressor system into the existing plant.

 

Services:

  • Variant studies and process engineering concept
  • Building and installation concept for integration into the existing plant
  • Piping and apparatus engineering integration into the existing plant
  • Operational and control engineering integration into the existing plant
  • Determination of investment costs and ongoing operating costs
  • Realization date and resource plan

 

Key data:

  • Tube storage: Storage volume 5,000 Nm3, operating pressure: 70 bar
  • Spherical storage: Storage volume 15,000 Nm3, operating pressure 8 bar
  • One inlet control section: Capacity 40,000 Nm3/h, operating pressure 40 bar
  • Natural gas compressor system: Capacity 25,000 Nm3/h, operating pressure 70 bar
  • Outlet control sections: Capacity 80,000 Nm3/h, operating pressure 70 bar
  • Multi-circuit cooling system with cooling tower

 

Period: 2008